This round of APEC cooperation does not change which models are approved. It changes who in the Asia-Pacific can still get a data hall, power, and inference they can actually use.
- Policy: 2026–2030 is voluntary cooperation plus an annual review, not a shared procurement list.
- Industry: The next five years turn on whether GPUs, power, and cooling can scale together, not on card count alone.
- Market: Singapore, Japan, Korea, Hong Kong, and mainland China are not publishing the same kind of number. They cannot be ranked as capacity.
- Deployment: Choose among an API, rented GPUs, and building your own by utilization. An agent still needs a separate machine for its tools.
As of 17 November 2026, the leaders’ meeting in Shenzhen has not been held. “Plan” and “list price” below are not built capacity and not transaction prices.
What APEC is set up to push over these five years
| Item | Confirmed | What it means for the industry |
|---|---|---|
| Aim | Secure, accessible, and reliable ecosystems; capacity building; encouraging infrastructure investment that uses energy-efficient technology. Cloud, data centers, power sources, and grids are named | Cooperation is about who can use AI, and whether data halls and power can actually be financed |
| Horizon | Forums fold it into work plans. DESG and the Telecommunications Working Group review it jointly each year. A final review in 2030. It is written into the annual AIDER report | A five-year window, not a 2026 equipment list |
| Who takes part | Each economy’s AI policy can differ. Public-private cooperation is encouraged, and ABAC is named. Korea funds and runs an Asia-Pacific AI Center for capacity building and information sharing | There is no regional regulator and no compute scheduler |
| Boundary | No GPU model, agent framework, capacity figure, or PUE | Later judgments cannot be rewritten as standards the document already set |
Where compute demand gets stuck
| 2,185 EFLOPS | 177% | 71.4% |
|---|---|---|
| Mainland China intelligent compute, as of June 2026 | Year on year | National rack-up rate of compute facilities |
Source: Ministry of Industry and Information Technology, State Council Information Office briefing, 20 July 2026. The figure is FP16, not data-center megawatts.
| What is scarce | What changes next (a judgment, not a new official forecast) |
|---|---|
| GPU compute | Training and inference are still growing. The basis is the 177% above, not a fresh growth forecast |
| Power | Expansion depends more and more on the grid. Singapore allocates new megawatts against green power. Korea and mainland China write power into their data-center plans |
| Cooling | High-density halls are moving toward liquid cooling. The basis is Singapore’s quota of 21 August 2026, which requires liquid cooling, not an installed share for the whole region |
What changes for models, open source, and agents
| Direction | Policy or industry signal already on record | Likely effect (judgment) |
|---|---|---|
| Open models | The Chengdu statement of 23 July 2026 encourages open-source projects, subject to security, data protection, and intellectual property | Companies have more options if they host a model themselves. Open source is not required |
| AI agents | On 16 July 2026 Korea set out a plan for “one AI agent per person.” That is a national plan, not an APEC clause | If it is rolled out, inference calls and concurrency may rise. It is still a plan |
| Data centers | The first phase planned by SK, GS, and Naver is about KRW 550 trillion, for 8.4 GW. That is not money already spent | Large-scale compute infrastructure will keep expanding. Whether it lands depends on power and siting |
Where each of the five markets is strong
These figures cannot be ranked as a capacity league. Some are megawatts already operating, some are plans for new builds, one is FP16 compute, and one is submarine-cable capacity.
| Place | Position | What the number measures | Published figure |
|---|---|---|---|
| Singapore | Green power and data centers | Existing capacity, plus new quota issued by application | May 2024: more than 1.4 GW already, and more than 70 facilities. On 21 August 2026, 200 MW was provisionally allocated, 50 MW to each of four operators, and more than half of the power must be green |
| Japan | GPU cloud | A company’s planned grid connection, plus a government subsidy cap. Not national capacity in operation | SoftBank’s May 2026 plan: Tomakomai starts at 50 MW in FY2026 and can grow to 300 MW; Sakai is targeted for FY2027 at 140 MW, on the order of 100,000 H200s. In April 2024 METI recognized five GPU-cloud projects, with a combined subsidy cap of ¥72.5 billion |
| Korea | Very large investment | New-build plans from government and companies, not operating load | 29 June 2026: phase one is 8.4 GW (SK 5, GS 2.4, Naver 1). SK’s 5 GW is planned to reach 15 GW by 2035. The southwest has a separate plan for about KRW 800 trillion and four memory fabs |
| Hong Kong | International connectivity | The official figure is external telecommunications capacity. Data-hall megawatts are third-party | Equipped external capacity at the end of June 2026 was 374,067.79 Gbps. As of July 2026 there were 13 submarine-cable systems and 10 landing stations. DC Byte, cited in a King & Wood Mallesons guide: 582 MW in operation in September 2026 |
| Mainland China | Intelligent-compute clusters | Intelligent compute (FP16), not data-hall megawatts | 52 facilities above 10,000 accelerators. The 2030 target is 9,800 EFLOPS, and new large facilities are to keep PUE under 1.2. For 2,185 EFLOPS, 177%, and 71.4%, see the previous section |
How a company chooses an API, rented GPUs, or its own cluster
The table is the 7 November 2026 on-demand list price for an 8-GPU NVIDIA H100 node, divided by 8. CPU, memory, and network differ across the tiers. These are not transaction prices.
| Provider | Product | Per GPU-hour |
|---|---|---|
| AWS | p5.48xlarge, US East | US$6.88 |
| Google Cloud | a3-highgpu-8g, Iowa | US$11.06 |
| CoreWeave | HGX H100, North America | US$6.16 |
| AWS | The same instance, Tokyo, price list of 16 November | US$8.60 |
Tokyo’s list price is about 25% above US East. Do not budget an Asia-Pacific deployment from the US East rate. Power and cooling are not in this table.
| Use | Fits when | Main cost | Does not fit |
|---|---|---|---|
| Cloud API | Calls are intermittent, and the data may leave the jurisdiction for that API | Per token generated. Waiting on tools usually does not bill a GPU | Weights and data must stay inside a named jurisdiction |
| Hourly GPU rental | A specific open model, with fine-tuning or batch inference that comes in bursts | Every hour the card is held, including idle time while tools run | Utilization is low, but a whole pool is reserved by the month |
| Long reservation or self-build | Utilization is high, and the team can handle power, cooling, and cluster networking | Machines, power, cooling, and operations. Idle time still costs money | A prototype that can be switched off over the weekend |
| A persistent tool machine, plus an API or a small model | The agent must keep a browser, code, or local files open | That machine is a separate bill. Inference still follows the three rows above | Using an H100 hour to stand in for the tool machine |
If the tools must run on macOS — Xcode, a simulator, or a small model that fits in memory — that machine and an H100 hour are two bills. For how to size memory, see Can Mac mini run local AI models?.
If a new infrastructure commitment appears after 19 November, add it only to the table in the first section. Choosing an API, rented cards, or a self-build still depends on utilization, whether the data can leave the jurisdiction, and whether the tools must stay on a particular operating system.
- Primary texts: APEC AI Initiative (2026–2030); Chengdu ministerial statement, 23 July 2026.
- Singapore: IMDA Green Data Centre Roadmap; EDB / IMDA, 21 August 2026.
- Japan: METI, 19 April 2024. SoftBank’s megawatts come from CNET Japan’s write-up of the May 2026 mid-term plan.
- Korea: Ministry of Climate, Energy and Environment, 29 June 2026; Ministry of Science and ICT, 16 July 2026.
- Hong Kong: Office of the Communications Authority; submarine cables. The 582 MW figure is DC Byte, as cited in a King & Wood Mallesons guide.
- Mainland China: 788 EFLOPS in June 2025; more than 1,590 EFLOPS at the end of 2025; 2,185 EFLOPS (FP16) in June 2026. 9,800 EFLOPS is the 15th Five-Year Plan target.
- H100 list prices: Rillor, 7 November 2026; Tokyo from GPU Ledger, 16 November 2026.